Click the project links (») below to view project details.
  • » Bluffton Road Bridge over St. Mary's River
    • USI Consultants is completing the bridge superstructure design for the Bluffton Road Bridge over the St. Mary’s River. 
    • The project will remove the current load postings for the bridge, rehabilitate the bridge to lengthen its life span, widen sidewalks on the bridge for accessibility to the Rivergreenway and Foster Park and improve scour protection.  
    • This is a federal project with the Indiana Department of Transportation (INDOT) that has cost sharing of 80/20 with the City of Fort Wayne.
    • A public meeting was held on 02/09/2022 and another meeting is anticipated to be held before design is completed.
    • Bluffton Road Bridge Project will be let through INDOT, and construction is estimated to begin in the fall of 2024 or spring of 2025.

    •  

      Click links to view plans and renderings:

  •  

    » Goeglein Road Bridge over Bullerman Drain
    • Beam, Longest and Neff L.L.C. is completing the bridge superstructure design for Goeglein Road Bridge over the Bullerman Ditch.
    • The project will remove the current load postings for the bridge, rehabilitate the bridge to lengthen its life span, widen sidewalks on the bridge for pedestrians, and to improve scour protection.
    • This is a federal project with the Indiana Department of Transportation (INDOT) that has cost sharing of 80/20 with the City of Fort Wayne.
    • Goeglein Road Bridge Project will be let through INDOT, and construction is estimated to begin in the fall of 2024 or spring of 2025. 
    • pdfGeoglein Road - Stage 2